Concrete Volume Calculator
Calculate concrete volume required for slabs, footings, and columns.
Calculator
No signup required. Results are indicative—verify for your standards.
Net volume: 3.600 m³
Order quantity (with 10% wastage): 3.96 m³
Formula
Rectangular slab/footing: V = L × W × H (m³). Circular column: V = π × (D/2)² × H. Add 5–10% wastage allowance to the calculated volume.
Example calculation
Foundation slab 6 m × 4 m × 0.15 m: V = 6 × 4 × 0.15 = 3.6 m³. Add 10% wastage: 3.6 × 1.1 = 3.96 m³ → order 4 m³.
Engineering notes
Ready-mix concrete is typically ordered in 0.5 m³ increments. Standard mix proportions: M20 (1:1.5:3) for general structural use, M25 (1:1:2) for columns and beams, M30 for industrial floors. Always add 10% overage for pours to account for losses and uneven subgrade.
When to use this calculator
- Construction BOQ — calculate concrete quantities for foundation, slab, columns, and beams for a building
- RMC ordering — determine ready-mix concrete order quantity before pouring begins
- Cost estimation — compute concrete cost from volume × current RMC price per m³
- Industrial flooring — calculate concrete for plant room floors, equipment plinths, and paving
- Civil works tendering — prepare concrete volume take-off for civil subcontract quotation
Frequently asked questions
- What concrete grade should I use for different applications?
- M15 (15 MPa): mass concrete, blinding layers, non-structural fill. M20 (20 MPa): general slabs, footings, beams — minimum for reinforced concrete per IS 456. M25 (25 MPa): columns, retaining walls, industrial floors with moderate loads. M30 (30 MPa): heavy industrial floors, high-rise columns, water-retaining structures. M35+ (35 MPa+): bridges, precast structural elements, heavy foundations.
- How do I calculate the number of cement bags, sand, and aggregate needed?
- For M20 concrete (1:1.5:3 by volume), per 1 m³ of concrete approximately: cement 8–8.5 bags (50 kg each), sand 0.42 m³, aggregate (20 mm) 0.84 m³. For M25 (1:1:2): cement 10.5–11 bags, sand 0.35 m³, aggregate 0.70 m³. These are approximate — use the IS 10262 mix design procedure for critical structural elements to determine exact proportions based on aggregate properties.
- Why should I add a wastage factor to my concrete calculation?
- Wastage occurs from: uneven subgrade requiring more concrete to achieve design thickness, spillage during placing and vibration, over-pour at edges and formwork edges, and concrete that adheres to the mixer drum and chutes. Standard wastage allowances: 5% for simple pours with good formwork, 10% for general structural work, 15% for complex formwork with many penetrations. Under-ordering concrete is expensive (emergency additional pour) so always order with adequate buffer.
Related calculators
Looking for industrial vendors in India?
Post your procurement requirement free on the CI Suite Pro marketplace. Engineering, AMC, logistics, civil, IT — receive proposals from verified vendors within 24 hours.
