Manufacturing#OEE#OEE formula#OEE calculation

How to Calculate OEE (Overall Equipment Effectiveness) — Formula, Examples & Free Calculator

OEE = Availability × Performance × Quality. This guide walks through the exact 3-step calculation with a worked factory example, industry benchmarks, the six big losses breakdown, and a free OEE calculator.

Published 15 June 2025Updated 12 June 202610 min read

OEE (Overall Equipment Effectiveness) formula:

OEE = Availability × Performance × Quality

Quick example: A machine with 87.5% availability, 95.2% performance, and 97.0% quality has an OEE of 80.8%. World-class OEE: 85%+. Industry average: 60%.

Use the free OEE Calculator at cisuitepro.com/calculators/oee-calculator to compute your OEE instantly from shift data — no signup required.

OEE is the most widely-used KPI in discrete manufacturing. It captures all three categories of production loss in a single number: downtime (Availability), speed loss (Performance), and defects (Quality). A score of 100% means you are producing only good parts, as fast as possible, with zero unplanned downtime.

The OEE Formula

OEE is the product of three factors, each expressed as a percentage:

OEE = Availability × Performance × Quality

Each factor captures a different type of loss:

  • Availability — time lost to unplanned downtime and changeovers
  • Performance — speed losses: running slower than rated speed or micro-stops
  • Quality — defects, scrap, and rework that result in non-conforming parts

Availability

Availability measures the fraction of Planned Production Time during which the equipment was actually running.

Availability = Run Time ÷ Planned Production Time

Run Time = Planned Production Time − Stop Time

Stop Time includes all unplanned downtime events (breakdowns, waiting for materials, waiting for operators) plus planned downtime that occurs during what should be production time (changeovers, setups, inspections).

Example: A machine is scheduled to run 480 minutes per shift. During the shift, there are two breakdowns totalling 45 minutes and a 30-minute changeover. Stop Time = 45 + 30 = 75 minutes Run Time = 480 − 75 = 405 minutes Availability = 405 ÷ 480 = 84.4%

Performance

Performance captures speed losses — situations where the equipment is running but not at its maximum rated speed.

Performance = (Ideal Cycle Time × Total Count) ÷ Run Time

Or equivalently:

Performance = Actual Throughput Rate ÷ Ideal Throughput Rate

Ideal Cycle Time is the theoretical minimum time to produce one part. Total Count is the total number of parts produced during the shift, including defects.

Example (continuing from above): The machine produced 380 parts during 405 minutes of Run Time. The ideal cycle time is 1.0 minute per part. Expected output = 405 ÷ 1.0 = 405 parts Actual output = 380 parts Performance = (1.0 × 380) ÷ 405 = 93.8%

Note: Performance can occasionally exceed 100% if the equipment is run faster than its rated speed. Most practitioners cap Performance at 100% to avoid masking quality or maintenance risks.

Quality

Quality represents the proportion of total output that meets specification on the first pass — no rework required.

Quality = Good Count ÷ Total Count

Example (continuing): Of 380 parts produced, 12 were scrapped due to dimensional out-of-tolerance. Good Count = 380 − 12 = 368 Quality = 368 ÷ 380 = 96.8%

Putting It All Together

Using the three values from our example:

OEE = 84.4% × 93.8% × 96.8% = 76.6%

This machine is operating at 76.6% of its theoretical maximum capacity. While above the global average of ~60%, it still has meaningful room to improve before reaching the world-class target of 85%.

FactorValueLosses Captured
Availability84.4%Breakdowns, changeovers, material wait
Performance93.8%Reduced speed, micro-stops, idling
Quality96.8%Scrap, rework, startup rejects
OEE76.6%Combined productive efficiency

Industry OEE Benchmarks

OEE benchmarks vary significantly by industry due to inherent differences in process complexity, changeover frequency, and part complexity.

IndustryTypical OEE RangeWorld-Class Target
Automotive assembly65–80%85%+
Electronics / PCB55–75%80%+
Food & beverage50–70%75%+
Pharmaceutical45–65%75%+
CNC machining / job shop50–70%80%+
Plastic injection moulding60–80%85%+
Printing / packaging55–75%80%+

The Six Big Losses

The OEE framework was designed around Six Big Losses — categories of waste that reduce manufacturing effectiveness. Every loss maps back to one of the three OEE factors:

Loss CategoryOEE FactorExamples
Equipment breakdownAvailabilityMotor failure, hydraulic leak
Setup & adjustmentAvailabilityChangeover, tooling change
Idling & minor stopsPerformanceSensor trip, jam clearance < 5 min
Reduced speedPerformanceWorn tooling, operator caution
Process defectsQualityScrap during normal production
Startup / yield lossesQualityWarm-up rejects, first-off inspection

How to Improve OEE

Improving OEE is not about working harder — it is about removing systematic waste from the production process. Here are the highest-leverage interventions for each factor:

  • Availability: Implement Autonomous Maintenance (AM) — train operators to clean, inspect, and lubricate machines daily. Studies show AM can reduce breakdowns by 30–50% within 6 months.
  • Availability: Use SMED (Single-Minute Exchange of Die) to reduce changeover time. Converting internal setup steps to external can cut changeover time by 50%.
  • Performance: Investigate and eliminate "micro-stops" — stoppages under 5 minutes that are rarely logged but cumulatively steal 5–15% of shift time in many plants.
  • Performance: Check if operators are running below ideal speed as a precaution. Often machines are de-rated due to historical quality problems that have since been resolved.
  • Quality: Conduct a Pareto analysis of defect types. In most plants, 80% of scrap comes from 20% of defect types. Fix the top two or three root causes first.
  • Quality: Use Statistical Process Control (SPC) charts to catch process drift before it creates out-of-spec parts.

OEE vs. TEEP

OEE measures efficiency within Planned Production Time — it does not account for time the machine is simply not scheduled to run. TEEP (Total Effective Equipment Performance) extends OEE by including all calendar time:

TEEP = OEE × Utilisation Utilisation = Planned Production Time ÷ Total Calendar Time

A machine running one 8-hour shift, 5 days a week has a Utilisation of about 24%. If that machine has an OEE of 85%, its TEEP is only 85% × 24% = 20.4%.

TEEP is useful when evaluating capital investment decisions — if TEEP is very low, adding capacity may not be the right answer. Improving scheduling to increase utilisation could deliver the same outcome at much lower cost.

Common OEE Calculation Mistakes

Even experienced engineers make these mistakes when calculating OEE:

  • Including planned maintenance in Stop Time: Planned Preventive Maintenance (PM) performed outside of production hours should not be counted as availability loss. Only include stops that occur during Planned Production Time.
  • Using the wrong Ideal Cycle Time: The ideal cycle time must reflect the true theoretical maximum speed of the equipment — not the standard or average rate used for scheduling.
  • Double-counting losses: If a breakdown causes both downtime (Availability) and slow restarts producing defects (Quality), only count each unit of loss once in its correct category.
  • Aggregating across dissimilar equipment: OEE is most actionable at the individual machine level. A plant-wide average can mask a single bottleneck machine dragging down the whole line.
  • Not separating startup losses from process defects: Startup rejects during warm-up are a different root cause from in-process defects and should be tracked separately even though both reduce Quality.

OEE Calculation: Step-by-Step Example

Here is a complete OEE calculation for a single production shift:

Shift data: Planned time = 480 min. Breakdowns = 30 min. Changeover = 15 min. Ideal cycle time = 1 min/unit. Units produced = 395. Rejected units = 8.

Step 1 — Availability: Run time = 480 − 30 − 15 = 435 min Availability = 435 ÷ 480 = 90.6%

Step 2 — Performance: Performance = (1 × 395) ÷ 435 = 90.8%

Step 3 — Quality: Good units = 395 − 8 = 387 Quality = 387 ÷ 395 = 98.0%

OEE = 90.6% × 90.8% × 98.0% = 80.6%

This machine is running at 80.6% OEE — above the global average of 60% but still short of the world-class target of 85%. The biggest loss is Performance (micro-stops and reduced speed) — that is the first area to investigate.

StepCalculationResult
Availability435 ÷ 48090.6%
Performance(1 × 395) ÷ 43590.8%
Quality387 ÷ 39598.0%
OEE90.6% × 90.8% × 98.0%80.6%

Start Calculating OEE Today

To calculate OEE you need four data points from your shift log: planned production time, total downtime, total units produced, and good units produced.

Enter those numbers into our free OEE Calculator at cisuitepro.com/calculators/oee-calculator — it shows Availability, Performance, Quality, and OEE% instantly, with a colour-coded benchmark so you know exactly where you stand against world-class 85%.

Collect at least one week of shift data before drawing conclusions. A single shift result can be misleading; a weekly average is a reliable baseline.

Frequently Asked Questions

What is the OEE formula?

OEE = Availability × Performance × Quality. Availability = (Planned time − Downtime) ÷ Planned time. Performance = (Ideal cycle time × Total units produced) ÷ Run time. Quality = Good units ÷ Total units produced. Multiply all three as decimals to get OEE as a decimal, then convert to a percentage.

How do you calculate OEE with an example?

Example: Planned time = 480 min. Downtime = 45 min. Ideal cycle time = 1 min/unit. Units produced = 395. Good units = 387. Availability = (480−45)÷480 = 90.6%. Performance = (1×395)÷435 = 90.8%. Quality = 387÷395 = 98.0%. OEE = 90.6% × 90.8% × 98.0% = 80.6%. World-class is 85%.

How do you calculate OEE Availability?

Availability = Run Time ÷ Planned Production Time × 100. Run Time = Planned Production Time − Stop Time. Stop Time includes all unplanned downtime (breakdowns, waiting for materials) and planned downtime that falls within production time (changeovers, setups). Example: planned 480 min, stops 60 min → Availability = 420÷480 = 87.5%.

How do you calculate OEE Performance?

Performance = (Ideal Cycle Time × Total Units Produced) ÷ Run Time × 100. Ideal Cycle Time is the theoretical minimum time per unit at full speed. Total Units includes both good and rejected parts. Example: ideal cycle 1 min/unit, 380 units produced, run time 420 min → Performance = (1×380)÷420 = 90.5%. Performance measures speed losses — micro-stops and reduced speed.

What is a good OEE score?

OEE 85%+ is world-class. 60–85% is typical for manufacturers with active improvement programmes. Below 60% is common in plants without structured maintenance. For individual components: world-class availability >90%, performance >95%, quality >99.9%. Most plants suffer most in Performance (speed losses) followed by Availability (breakdowns and changeovers).

What is the difference between OEE and TEEP?

OEE measures efficiency within Planned Production Time (scheduled shift hours). TEEP (Total Effective Equipment Performance) = OEE × Utilisation, where Utilisation = Planned Production Time ÷ Total Calendar Time. A machine running one 8-hour shift with 85% OEE has a TEEP of only 85% × 24% = 20.4%. TEEP is used for capital investment decisions — if TEEP is very low, better scheduling may be more valuable than buying new equipment.

How do the six big losses map to OEE components?

Availability losses: (1) Equipment breakdowns, (2) Setup and adjustment (changeover). Performance losses: (3) Minor stoppages and idling (< 5 min, often unlogged), (4) Reduced speed below rated rate. Quality losses: (5) Process defects during normal production, (6) Startup rejects during warm-up. Improving OEE means eliminating these six losses in priority order — tackle the biggest loss first.

Free calculators mentioned in this article

More articles

Need industrial vendors for your project in India?

Post your procurement requirement free on CI Suite Pro. Engineering, AMC, logistics, civil works — receive verified vendor proposals within 24 hours. No fee, no commission.